Kick-off Meeting

A kick-off meeting brings the project participants together to establish a shared starting point. It confirms the problem, scope, roles, working arrangements and immediate actions. It is a coordination activity, not evidence that the causes or solution have been agreed.

Expected output: A decision and action record confirming how the project will start.

01 · Purpose

Why and when to use it

Why?

It exposes different interpretations early and turns a project announcement into a practical agreement about how work will begin.

When?

Hold it after a draft mandate exists and before coordinated investigation begins; use a follow-up when key uncertainties remain.

Who takes part? The leader facilitates, the sponsor confirms the mandate, and team members and key interface owners contribute.

02 · Application

How to apply it

Start with: Draft charter, scope, proposed roles, initial schedule, dependencies and questions needing agreement.

  1. Share a concise draft charter and agenda in advance.
  2. Explain the performance gap and distinguish evidence from assumptions.
  3. Check scope, objectives, responsibilities and decision authority.
  4. Discuss working arrangements, availability and initial risks.
  5. Agree the first actions with owners and dates.
  6. Circulate decisions and unresolved questions; confirm attendance does not substitute for approval.

03 · Example

A warehouse dispatch project

Original illustrative example. All quantities, targets, roles and timings below are fictional teaching assumptions, not findings from a real project.

Agenda itemTimeRequired result
Purpose and problem10 minutesCommon understanding of the provisional dispatch gap.
Scope and roles15 minutesConfirmed boundaries and named responsibility holders.
Plan and constraints15 minutesAgreed initial sequence, availability and dependencies.
Questions and actions20 minutesAction log with owners, deadlines and unresolved approvals.

04 · Interpretation

What the result tells you

A successful meeting produces clear next actions and identifies disagreements needing resolution. If the team cannot agree on a measure or scope boundary, record the issue rather than implying consensus.

Completion check: A decision and action record confirming how the project will start.

05 · Judgement

Mistakes and limitations

Common mistakes

  • Using the meeting only as a sponsor presentation.
  • Allowing immediate solution selection to replace investigation.
  • Leaving with actions that have no owner or deadline.

Limits of the tool

One meeting does not secure continuing engagement. People absent from an important decision may need a separate discussion; maintain communication and revisit agreements as evidence changes.

07 · Reading

Sources and further reading

Toolset backbone: Six Sigma+Lean Toolset: Mindset for Successful Implementation of Improvement Projects, second edition, edited by Stephan Lunau, with Renata Meran, Alexander John, Olin Roenpage and Christian Staudter (Springer, 2013). This reference identifies the toolset; the book text was not available for a chapter-level comparison in this development pass. The explanations, application sequence and fictional examples here are original LeanTrainingLab teaching material. Linked readings provide background; they do not prescribe every example or target.